The Electricity company of Ghana is required to shed  a total of 390 megawatts of power  Monday.

According to regions:

Greater Accra will shed a total of (130MW),

Ashanti (80MW),

ADVERTISEMENT

Tema (60MW),

Western (40MW),

Central (30MW),

Eastern (30MW)

Volta (20MW)

ADVERTISEMENT

ECG is to shed load between 6 am and 6pm due to  the insufficient power generation, and it must be according to the schedule below

Accra… 130MW Ashanti…. 80MW

Tema…….. 60MW

Western…. 40MW

Central….. 30MW

ADVERTISEMENT

Eastern…. 30MW

Volta…… 20MW

Total….. 390MW

Note: Group A is coming ON Group B is going OFF Group C is going 24hrs

JOIN OUR PULSE COMMUNITY!

Unblock notifications in browser settings.
ADVERTISEMENT

Eyewitness? Submit your stories now via social or:

Email: eyewitness@pulse.com.gh

ADVERTISEMENT