ADVERTISEMENT

Conduct criminal investigations into Saglemi housing project - Attorney General

Ms Gloria Akuffo, the Attorney-General and Minister of Justice has recommended criminal investigations into the conduct of actors in the $200-million, 5,000-unit Saglemi housing project.

Saglemi Housing Project

A letter dated May 8, 2019, signed by the Attorney General and addressed to the Minister of Works and Housing, Samuel Atta Akyea, indicated that the parties to the contract, namely the government of Ghana and Construtora OAS Ghana Limited, were bound by the agreed accrued rights and obligations.

The Attorney-General’s advice was premised on the absence of a valid explanation for variations in the original contract from 5,000 housing units to 1,502 units for the same $200 million contract amount.

Following from the accrued rights and obligations of the parties, the then-Attorney-General advised that the Ministry of Works and Housing had the right to demand specific performance of the obligations of the contractor as contained in the original agreement.

The advice from the Attorney General further stated that the original contract expired in June 2017 and for that reason, "there can be no termination of a non-existent agreement as requested by the ministry".

ADVERTISEMENT

The Ministry of Works and Housing had requested the Attorney General to advise them on the options available for the termination or otherwise of the contract.

As a result, the Attorney General said: "The agreement, having expired in June 2017, the purported notice of termination by the contractor has no basis in law and is, therefore, of no effect".

"The ministry is, therefore, advised to write formally to the contractor rejecting the purported notice of termination," the letter stated in response to the contractor's notice of termination.

The Attorney General, after reviewing the documents the Ministry of Works and Housing submitted to her outfit, observed that both the Executive and parliamentary approval for the Saglemi project was for 5,000 housing units for the cost of $200 million.

ADVERTISEMENT

"From the documents reviewed, there is no evidence justifying the variation of the scope of the agreement in the first and re-stated agreement signed by then-Minister of Works and Housing, Mr Collins Dauda, which reduced the number of housing units to be constructed from 5,000 to 1,502 though the price remained $200 million," it said.

It noted that the restated agreement should have been sent back to Parliament for approval, following the substantial variation and failure which had rendered the restated agreement null and void.

It added that although the Chief Director of the Ministry of Works and Housing, Alhaji Ziblim Yakubu, signed the second and restated agreement dated 21 December 2016 with the contractor; there was no evidence to show the Chief Director was clothed with the capacity to review the contract.

On October 31, 2012, parliament granted an approval of $200 million for the construction of the affordable houses at Saglemi near Tsopoli in the Ningo Prampram District of the Greater Accra Region.

In November 2013, former President John Mahama cut the sod for the first phase of the Housing Project, in what was described as the most ambitious housing project in the West Africa sub-region.

ADVERTISEMENT

The 300-acre 1,502-housing unit facility, which comprises one to three bedroom apartments and town houses, is 80 per cent complete and earmarked to be occupied by residents in the near future, therefore helping to reduce the national housing deficit.

The over 1,000 housing project has been abandoned by the NPP-led administration.

JOIN OUR PULSE COMMUNITY!

Unblock notifications in browser settings.
ADVERTISEMENT

Eyewitness? Submit your stories now via social or:

Email: eyewitness@pulse.com.gh

ADVERTISEMENT