Advertisement

ECG sheds 390MW of power today

___4287370___https:______static.pulse.com.gh___webservice___escenic___binary___4287370___2015___10___23___11___dumso
___4287370___https:______static.pulse.com.gh___webservice___escenic___binary___4287370___2015___10___23___11___dumso
This is upon the request of the Ghana Grid Company Gridco, due to a massive drop in generation owing to some temporary  problems affecting some of the major thermal plants in the country.
Advertisement

The Electricity company of Ghana is required to shed  a total of 390 megawatts of power  Monday.

Advertisement

According to regions:

Greater Accra will shed a total of (130MW),

Ashanti (80MW),

Tema (60MW),

Advertisement

Western (40MW),

Central (30MW),

Eastern (30MW)

Volta (20MW)

ECG is to shed load between 6 am and 6pm due to  the insufficient power generation, and it must be according to the schedule below

Advertisement

Accra… 130MW Ashanti…. 80MW

Tema…….. 60MW

Western…. 40MW

Central….. 30MW

Eastern…. 30MW

Advertisement

Volta…… 20MW

Total….. 390MW

Note: Group A is coming ON Group B is going OFF Group C is going 24hrs

Advertisement